Critical Path Method (CPM)

CPM-2In this video we are going to explain the concept of critical path method.

This video covers the following:

  1. Critical Path
  2. Critical Path Method
  3. Calculation of early start, early finish, late start, late finish

Critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible duration. Typically, it determines the time the project will take. Any deviation in this path can affect the project duration in a negative or positive way.